Guide · Approvals

Licences and approvals: net billing, auxiliary and wheeling

Updated 16 October 2026 · Sources listed at the end

Any solar system that connects to the JPS grid needs approval. Which licence you need depends on one question: do you want to send power back to the grid?

Who is involved

  • Ministry of Energy — issues the licences and runs the net billing programme.
  • JPS — signs the interconnection contract and connects your system.
  • Office of Utilities Regulation (OUR) — sets the rate JPS pays for exported power.
  • Government Electrical Regulator (GER) — registers the electrical inspectors who certify your system.
  • Bureau of Standards Jamaica (BSJ) — approves inverters and sets equipment standards. Check an inverter.

Three licence routes

 Net billingAuxiliary connectionPower wheeling
What it allowsUse your solar power and sell the excess to JPSConnect to the grid, but no sellingGenerate at one property, use the power at another
System sizeUp to 10 kW residential; 100 kW commercialNo published limitOver 1 MW
EquipmentBSJ-approved inverterBSJ-approved inverter and export blocking deviceBSJ-approved inverter
Good forMost homes and small businessesLarger homes, EV charging, high daytime useLarge businesses with several sites
Note: only draft regulations exist for auxiliary connections and wheeling, and installers have reported difficulty applying for an auxiliary licence. Ask your installer how they will handle it before you sign.

What you need to apply

  • A completed application form
  • Proof you are a JPS customer (customer number and premises number)
  • Proof you own the property, or the owner’s written permission
  • A proposed electrical line diagram certified by a licensed electrician
  • A J$10,000 non-refundable processing fee

Step by step

Phase 1 — Licence

  1. Hire an installer, who prepares the application documents.
  2. Submit the application to the Ministry.
  3. The Ministry sends a letter when the application is approved.
  4. Pay the licence fee — J$1,500 per kW of excess electricity permitted.
  5. The licence is issued.

Phase 2 — Contract, install and commission

  1. Your installer prepares and submits the contract to JPS.
  2. JPS reviews and signs it, and shares copies with the Ministry and OUR.
  3. The system is installed.
  4. A GER-registered licensed electrician inspects and certifies it.
  5. You give JPS the inspection certificate, pay a one-time use-of-system charge, and the system is commissioned.

Building permits

Some installations also need a building or environmental permit. Check with your parish municipal corporation (Local Building Authority) — contact details for every local authority are at localauthorities.gov.jm.

What if I skip the licence?

The Jamaica Renewable Energy Association has estimated that around half of systems never apply for a licence, citing a slow and costly process. It is tempting, especially for systems over 10 kW. But an unlicensed grid-tied system earns nothing for exported power, may have to be modified later, and can raise safety issues for line workers if it is not set up to shut off during outages.

The process is changing: the Government has said an online application platform is due by December 2026, and that licence fees and size caps are under review.

Ready to compare real quotes?
Answer a few questions and we will route you to providers serving your parish.